Stop signs added as Houser-Grandview intersection is opened

MUSCATINE, Iowa – The Houser Street leg of the Grandview Avenue intersection has been reopened to traffic but drivers should beware … the intersection will be a three-way stop through the remainder of the Grandview Avenue project.

Temporary stop signs were installed Friday after Heuer Construction, Inc., crews finished cleaning and sealing the intersection. The Mittman connection with Houser was opened Thursday.

Heuer Construction plans on continuing work on sidewalks and driveways from Franklin Street south toward Houser. The Sampson leg of the Grandview Avenue intersection is expected to be completed in mid- to late-September after all underground work is completed.

Drivers are reminded that there is a 25 mph speed limit and fines are doubled in the construction zone. Please be alert for construction workers and pay attention to traffic control devices.

WEST HILL PROJECT

Logan Street is closed to through traffic between Lucas and Climer streets with the contractor currently installing sewer from the alley toward Lucas. Once that section is completed, the contractor will place a temporary surface on the completed work and begin underground work from the alley towards Climer.

Local traffic will be permitted on Logan as the underground work is being completed. Once the underground work has been accomplished, the block of Logan will be prepped for paving and repaved.

Repaving Climer Street from the 700 block to High Street has been completed but the street will remain closed until sidewalk, driveways, and boxouts have been completed. Climer will be open to local traffic only once that is completed with the street closed at the High Street intersection.

Underground work on Climer from High to Logan will resume once work on Logan between Lucas and Climer has been completed. Advance notification will be given when this section of Climer is closed to traffic.

Lucas Street remains closed to traffic from Busch to West 8th as the contractor prepares this section of Lucas for repaving, which is scheduled for the week of August 22 depending on the weather.

Project work moving east on Lucas Street from the West 8th Street intersection continues with sanitary sewer pipe installed from West 8th up to the curve where Lucas becomes West 4th Street. Progressive closures of Lucas Street will occur moving to the east including the Main Street intersection. 

There will be limited access available with this section of Lucas reduced to one lane where the underground work is being completed. A temporary driving surface will be provided behind the underground work once the contractor determines it is safe to do so. Driveways along the work area will be inaccessible while the sewer is being installed, but the contractor will attempt to restore driveway access as quickly as possible with a temporary driving surface.

Categories
City of Muscatine Press Releases

Musser Park playground is reopened for public use

MUSCATINE, Iowa – The Musser Park playground reopened for public use today (July 13) following the completion of a trail extension from the levee to Oregon Street as part of the Southend Improvement Project. The playground area was closed June 9 as construction began on the trail extension.

A sidewalk between the trail and the playground area was also added during the trail construction. Additional Musser Park improvements include erecting a new shelter located close to the right field fence of the ball diamond. The new shelter should be completed by July 22, weather permitting.

New playground equipment is planned for Musser Park, but the equipment may not arrive until next spring due to supply chain issues.

Public use of Musser Park and the playground area are at the user’s own risk. Children should be supervised at all times. Please be aware of surroundings when walking in or around construction areas, and avoid these areas if at all possible.