Construction Update: 700 block of Climer closed for repaving

MUSCATINE, Iowa – The 700 block of Climer Street will be closed to all traffic beginning Monday as pavement restoration begins from the alley at 700 Climer to just past the High Street intersection. No parking signs were put out Friday morning ahead of the reconstruction work.

Haggerty Earthworks, Inc., indicated that the block will be prepped for paving on Monday and Tuesday with curb and gutter poured on both sides Wednesday and the driving lanes on Thursday, weather permitting. The tentative schedule calls for the block to reopen on August 15. Some lane restrictions may be implemented as the contractor completes driveway and sidewalk replacement.

The underground crew on Climer will be moving to the ravine between High Street and Logan to complete that section of sewer separation. Logan Street is tentatively scheduled to be closed to traffic on August 15 as underground work begins from Lucas to Climer. Area residents will be notified of the exact date of the street closure and the contractor will work with residents on access to their residences.

Meanwhile a second underground crew is wrapping up work at the Bush intersection on Lucas Street. That work is tentatively scheduled to be completed August 9, weather permitting. That crew will then move to the other side of West 8th Street and begin the sewer separation work toward Green Street.

Paving of Lucas from West 8th to Busch is tentatively scheduled to begin after the competition of the 700 block of Climer Street depending on the weather and other unforeseen circumstances.

Busch Street Detour – In order to maintain access to the residents of Busch Street, the City of Muscatine obtained permission from the owner of property located at the end of Greenwood Drive to use that private property to construct a connector path from the alley behind Busch Street to the end of Greenwood Drive. The path has been completed but is open to local traffic only. 

Using the route from Lucas down Greenwood Drive to the connector to the alley and to Busch provides access to all the homes on Busch during the Lucas intersection closure. Once the Busch-Lucas intersection is reopened, the temporary access road will be removed and reseeded to return it to its original condition.

Since the temporary access area runs next to a ravine, there have been problems in the past with people using that area to dump trash and other materials. If any such activity is witnessed during this period of use to access Busch Street please notify the Police Department.

GRANDVIEW WORK CONTINUES

Grandview Avenue is now open to two-way traffic. Drivers are reminded that Grandview from Main Street through the Houser intersection remains active construction zone with some lane restrictions as work continues. Please proceed with caution, slow down, and watch for construction workers. Speed limit is 25 mph and fines are doubled in construction zones.

Pavement restoration on Houser Street from Grandview Avenue to Mittman is scheduled to begin Saturday (Aug. 6). The contractor anticipates completing the intersection next week with plans to reopen that leg of the intersection around August 15, weather permitting.

The Sampson leg of the intersection will remain closed as underground work continues between Grandview Avenue to the Canadian Pacific Railroad crossing.

Heuer Construction, Inc., will resume work on sidewalks and driveways in Phase 1 of the Grandview Project after Houser is completed, and continue working on sidewalks and driveways in Phase 2 until the Sampson intersection is ready for paving.

___

The City of Muscatine and the Iowa DOT reminds motorists to drive with caution, obey the posted speed limit and other signs in the work area, and be aware that traffic fines for moving violations are at least double in work zones. As in all work zones, drivers should stay alert, allow ample space between vehicles, wear seat belts, and be aware of construction workers. Use an alternate route if possible.

Click on CONSTRUCTION to visit the Department of Public Works Construction Projects page where more information can be found on City of Muscatine construction projects. An interactive map is available showing current street closures and street work.

If you have a comment or concern, please email feedback@muscatineiowa.gov or pwrequest@muscatineiowa.gov. A staff member will respond within 24 hours.

Categories
City of Muscatine Press Releases

Lucas-West 8th intersection to be closed six weeks

MUSCATINE, Iowa – The intersection of West 8th and Lucas streets will be closed to all traffic beginning Monday (April 4) as part of Phase 5 of the West Hill Sanitary and Storm Sewer Separation Project. The full closure will last approximately six weeks depending on the weather.

 

Road Closure Diagram 4-4-2022 V2 (JPG)Limited access will be permitted on Lucas Street from Main Street on the east side of the intersection and from Busch Street on the west side. Limited access will also be permitted on West 8th Street from Broadway to the Lucas Street intersection and from Main Street to the Lucas Street intersection. The Whicher intersection will remain open.

 

In addition to the work at the Lucas and West 8th intersection, general contractor Haggerty Earthworks, LLC, plans to close Climer Street from West 8th to High starting on Wednesday (April 6). Local traffic only will be permitted as sanitary and storm sewer separation work begins on this segment of Phase 5.

 

The contractor anticipates keeping all driveways accessible for residents for as much as possible from Busch to Main on Lucas and from West 8th to High on Climer. Periodic closures will occur as underground work progresses. Full closures will occur during the removal and replacement of the pavement from curb to curb. Residents will be notified in advance of the full closures.

 

Sewer project work on Lucas Street in 2022 will focus on the area from Busch Street to the curve in Lucas Street just past Green Street and include the 900, 1300, 1400, and 1500 bl;ocks of Lucas.

 

Sewer project work on Climer Street in 2022 will begin in the 700 block of Climer and move toward the Lucas Street intersection. 

 

FULL DEPTH PATCHING CONTINUES

 

The two emergency repairs, on Hershey and Liberty, that are part of the 2022 Full Depth Patching Program are nearly complete but lane restrictions may continue into next week as concrete replacement continues. Liberty has been used as a detour during the Grandview Avenue reconstruction and the higher-than-normal traffic created buckles in the roadway.

 

Once the emergency repairs are completed, Heuer Construction, Inc., will move to 1608 Cedar Street (near the intersection with Parham).

 

Also included as part of the 2022 contract is Isett Avenue (Bidwell Road to the Heinz pedestrian entrance), Houser Street (Fulliam Avenue to Dawson Street), Stewart Road (Oregon Avenue to Wallace Street), Robin Road (Sunrise Circle east to end of the concrete), Frontage Road (Cleveland Street to Ford Avenue), and Devitt Avenue (Ridgewood Avenue to Pinefield Street). Additional emergency repairs may be added if time and money remain in the contract.

 

Additional traffic notes:

 

  • Heuer Construction, Inc., has closed one outside lane of Park Avenue from Washington to the Mad Creek Bridge on East 2nd Street to work on the Iowa DOT punch list for the Park Avenue 4-to-3 Lane Conversion Project that was substantially completed last fall.
  • Musser Street is closed from the intersection with Wisconsin and Baker to the Grandview intersection as the east side of the Musser-Grandview intersection is reconstructed as part of the Grandview Avenue Reconstruction Project.
  • Traffic restrictions continue on Grandview Avenue from Houser to Musser streets as underground work and pavement removal continue. The contractor maintains customer and delivery access to all businesses as Phase II of the Grandview Avenue Reconstruction Project continues. 

 

Drivers are reminded to slow down and use caution when travelling through the construction zone, obey traffic control devices, and be aware of workers. Use an alternate route if possible.

 

For more information on City of Muscatine construction projects click on CONSTRUCTION to visit the Department of Public Works Construction Projects page.

 

If you have a comment or concern, please email feedback@muscatineiowa.gov or pwrequest@muscatineiowa.gov. A staff member will respond within 24 hours.