MUSCATINE, Iowa – Lucas Street will be closed to all traffic from Green to West 4th Street, including the Green Street intersection, starting Wednesday (March 29) as work begins to prepare this section of Lucas Street for repaving. The West Hill Sanitary and Storm Sewer Separation Project underground work was completed last fall, but the weather did not permit repaving to be accomplished before the winter shutdown.
Local traffic only past the Main Street and West 4th Street intersections.
Northbound through traffic on Lucas will be detoured from West 4th Street onto Cherry Street, to West 5th Street, to Locust Street, and to West 8th Street. Southbound through traffic on Lucas will be detoured on to West 8th Street, to Locust Street, to West 5th Street, and to Cherry Street.
Please obey all traffic control signage and be alert for construction workers. The closure is expected to last 2-3 weeks, weather permitting.
MUSCATINE, Iowa – An updated Road Closure diagram has been issued for the West Hill Sanitary and Storm Sewer Separation Project Phase 5 as the project heads into the winter shutdown period.
Climer and Logan are fully open for residents and traffic.
Lucas Street is accessible from the West 8th Street up to but not through the Green Street intersection. The Main Street intersection is open to traffic.
Access to 970 Lucas is through a temporary path through the intersection from the south. The 900 block of Lucas and the Lucas/Green intersections are currently closed. However, the contractors have indicated that a temporary rock surface will be ready soon to allow access through the winter.
MUSCATINE, Iowa – The 200 block of West 2nd Street will be closed to traffic from noon Friday (Oct. 7) through noon Sunday (Oct. 9) for “Rockin’ On 2nd”. A stage will be set up near the Pearl City Chiropractic Building. Access to the Pine Street parking lot will be restricted or unavailable over the weekend.
The same block will be closed to traffic from noon Saturday, October 15, to noon on Sunday, October 16, for the “Couture & Canines Runway Show”. The event will be held from 7:30-8:30 p.m. with additional activities also planned.
Please use caution during these times and find alternate routes if possible. Additional parking is available in Riverside Park. Access to all businesses will be available.
MUSCATINE, Iowa – Lucas Street will be closed to traffic from West 8th to just past Main Street starting Wednesday morning, and travelers can expect Logan Street to be closed from Lucas to Climer within the next week or two according to the Muscatine Department of Public Works as part of the West Hill Area Sanitary and Storm Sewer Separation Project.
Repaving Climer Street from the 700 block to High Street is scheduled to begin Wednesday with curb and gutter on both sides of the street. The driving lanes are tentatively scheduled to be poured on Friday. Once cured, access to the Climer will be permitted with some lane restrictions as work on sidewalks and driveways is completed.
Project work will be moving east on Lucas Street from the West 8th Street intersection starting Wednesday morning (August 10) as the sanitary sewer pipe is replaced from West 8th up to the curve where Lucas becomes West 4th Street. Progressive closures of Lucas Street will occur moving to the east including the Main Street intersection.
There will be limited access available with Lucas reduced to one lane where the underground work is being completed. A temporary driving surface will be provided behind the underground work once the contractor determines it is safe to do so. Driveways along the work area will be inaccessible while the sewer is being installed, but the contractor will attempt to restore driveway access as quickly as possible with a temporary driving surface.
Project work near Logan Street will move west out of the ravine through the alley that goes toward Logan Street this week. During the winter new sanitary sewer pipe was placed from High Street toward the intersection of the east/west and the north/south portions of those alleys.
Ravine work began Tuesday and is expected to be into the alley intersection by Wednesday morning at which point all access to the alley up to Logan will be closed. As soon as the sewer is run up to Logan Street, access to driveways in the alleys will be restored. Eventually that portion of the alley will be paved but a rock surface will be placed as quickly as possible when the work in the alley is complete for access to the driveways.
MUSCATINE, Iowa – The intersection of West 8th and Lucas streets will be closed to all traffic beginning Monday (April 4) as part of Phase 5 of the West Hill Sanitary and Storm Sewer Separation Project. The full closure will last approximately six weeks depending on the weather.
Limited access will be permitted on Lucas Street from Main Street on the east side of the intersection and from Busch Street on the west side. Limited access will also be permitted on West 8th Street from Broadway to the Lucas Street intersection and from Main Street to the Lucas Street intersection. The Whicher intersection will remain open.
In addition to the work at the Lucas and West 8th intersection, general contractor Haggerty Earthworks, LLC, plans to close Climer Street from West 8th to High starting on Wednesday (April 6). Local traffic only will be permitted as sanitary and storm sewer separation work begins on this segment of Phase 5.
The contractor anticipates keeping all driveways accessible for residents for as much as possible from Busch to Main on Lucas and from West 8th to High on Climer. Periodic closures will occur as underground work progresses. Full closures will occur during the removal and replacement of the pavement from curb to curb. Residents will be notified in advance of the full closures.
Sewer project work on Lucas Street in 2022 will focus on the area from Busch Street to the curve in Lucas Street just past Green Street and include the 900, 1300, 1400, and 1500 bl;ocks of Lucas.
Sewer project work on Climer Street in 2022 will begin in the 700 block of Climer and move toward the Lucas Street intersection.
FULL DEPTH PATCHING CONTINUES
The two emergency repairs, on Hershey and Liberty, that are part of the 2022 Full Depth Patching Program are nearly complete but lane restrictions may continue into next week as concrete replacement continues. Liberty has been used as a detour during the Grandview Avenue reconstruction and the higher-than-normal traffic created buckles in the roadway.
Once the emergency repairs are completed, Heuer Construction, Inc., will move to 1608 Cedar Street (near the intersection with Parham).
Also included as part of the 2022 contract is Isett Avenue (Bidwell Road to the Heinz pedestrian entrance), Houser Street (Fulliam Avenue to Dawson Street), Stewart Road (Oregon Avenue to Wallace Street), Robin Road (Sunrise Circle east to end of the concrete), Frontage Road (Cleveland Street to Ford Avenue), and Devitt Avenue (Ridgewood Avenue to Pinefield Street). Additional emergency repairs may be added if time and money remain in the contract.
Additional traffic notes:
Heuer Construction, Inc., has closed one outside lane of Park Avenue from Washington to the Mad Creek Bridge on East 2nd Street to work on the Iowa DOT punch list for the Park Avenue 4-to-3 Lane Conversion Project that was substantially completed last fall.
Musser Street is closed from the intersection with Wisconsin and Baker to the Grandview intersection as the east side of the Musser-Grandview intersection is reconstructed as part of the Grandview Avenue Reconstruction Project.
Traffic restrictions continue on Grandview Avenue from Houser to Musser streets as underground work and pavement removal continue. The contractor maintains customer and delivery access to all businesses as Phase II of the Grandview Avenue Reconstruction Project continues.
Drivers are reminded to slow down and use caution when travelling through the construction zone, obey traffic control devices, and be aware of workers. Use an alternate route if possible.
For more information on City of Muscatine construction projects click on CONSTRUCTION to visit the Department of Public Works Construction Projects page.