City of Muscatine Press Releases

Pavement restoration begins on Lucas Street

MUSCATINE, Iowa – Construction work continues at two locations on Lucas Street in Muscatine as part of Phase V of the West Hill Sanitary and Storm Sewer Separation Project (WHSSSP).

Hagerty Earthworks, Inc., the prime contractor for this phase of the project, closed the intersection of Fletcher Avenue and Lucas Street Wednesday as underground work proceeded into the intersection. Lucas Street is now closed to traffic from Fletcher to Logan with residents on Fletcher and connected side streets detouring using Fletcher Avenue (down Miller’s Hill) to Hershey Avenue.

The intersection is tentatively scheduled to reopen in two weeks when underground work and backfilling of the area with rock has been completed.

West Hill - Fletcher intersection closed (JPG) 040623 Drivers are reminded that Greenwood Cemetery is not to be used as a shortcut around the construction on Lucas. Most of the entrances have been closed to traffic unless needed for funerals. Drivers using Hershey Avenue are urged to slow down and watch for increased traffic near the intersection with Fletcher Avenue.

Sub-contractor Heuer Construction, Inc., has prepared and started repaving the 900 block of Lucas Street including the intersection with Green Street. This underground work in this section of Lucas was completed last fall but there was not enough time for pavement restoration before the winter shutdown. A temporary rock surface was installed so the street could be open over the winter. The section is currently closed to all traffic. 

The westbound driving lane was poured Thursday (April 6) with the eastbound lane scheduled to be poured Monday, weather permitting. Driveways and sidewalks will also be replaced. This section is tentatively scheduled to be reopened April 21, weather permitting.

West Hill - Lucas Street westbound lane work (JPG) 040623 Hagerty still has sanitary and storm sewer separation work along with water main underground work on Climer Street from the Logan intersection to Lucas.

Once the 900 block of Lucas has been completed, Heuer is scheduled to complete pavement work in the alley off of Logan. Repaving of Lucas from Logan to Fletcher will be scheduled once the underground work on Lucas has been completed. The last segment to have the pavement restored will be Climer from Logan to Lucas. The pavement restoration timeline is dependent on the completion of underground work.

Hagerty Earthworks, Inc., was awarded the $6.03 million contract for Phase V of the WHSSSP. This phase includes replacing sewers on West 8th Street from Broadway to Lucas, on Climer Street from West 8th Street to Lucas, Logan Street from Lucas to Climer, Lucas Street from 912 Lucas to Fletcher Avenue, and through the ravine between Climer and Lucas. 

Grandview Avenue Reconstruction Project

The Grandview Avenue Reconstruction Project has resumed with lane restrictions in place at various locations from Main Street to Houser Street. Sidewalk work is underway from Musser to Houser on the west side of Grandview Avenue with southbound traffic moved to the middle lane. Sidewalk work on the east side will begin once the west side is completed.

Concrete and landscaping work also continues at the Oregon/Warren intersection with Grandview Avenue, and at several other locations on the west side of Grandview from Main Street to Warren.

Heuer Construction, Inc., was awarded the $7.74 million contract for the two-year Grandview Avenue Reconstruction Project that will remove and replace the pavement from Main Street to approximately 200 yards past Houser Street while adding sidewalks and additional streetscaping to provide a much more inviting corridor for residents and visitors.

 —

­Drivers are reminded to slow down and use caution when travelling through the construction zone, obey traffic control devices, and be aware of workers. Use an alternate route if possible.

For more information on City of Muscatine construction projects click on CONSTRUCTION to visit the Department of Public Works Construction Projects page.

To comment, provide a suggestion, or notify the city of an issue please visit MUSCATINE CONNECT, powered by SeeClickFix, or download the app from the Apple App store or Google Play. For more information visit CITIZEN REQUEST.

Additionally, if you have a comment or concern, please email feedback@muscatineiowa.gov or pwrequest@muscatineiowa.gov. A staff member will respond within 24 hours.

Categories
City of Muscatine Press Releases

Section of Lucas closed to traffic starting March 29

MUSCATINE, Iowa – Lucas Street will be closed to all traffic from Green to West 4th Street, including the Green Street intersection, starting Wednesday (March 29) as work begins to prepare this section of Lucas Street for repaving. The West Hill Sanitary and Storm Sewer Separation Project underground work was completed last fall, but the weather did not permit repaving to be accomplished before the winter shutdown.

Local traffic only past the Main Street and West 4th Street intersections.

Northbound through traffic on Lucas will be detoured from West 4th Street onto Cherry Street, to West 5th Street, to Locust Street, and to West 8th Street. Southbound through traffic on Lucas will be detoured on to West 8th Street, to Locust Street, to West 5th Street, and to Cherry Street.

Please obey all traffic control signage and be alert for construction workers. The closure is expected to last 2-3 weeks, weather permitting.

Categories
City of Muscatine Press Releases

Lucas-Logan intersection closed March 1-24; Detour announced

MUSCATINE, Iowa – The intersection of Lucas and Logan streets will be closed to all traffic for approximately three weeks starting Wednesday (March 1) afternoon as Phase 5 of the West Hill Sanitary and Storm Sewer Separation Project progresses. Work is expected to be completed by March 24, weather permitting.

Haggerty Earthworks, LLC, started placing a new sanitary main from Logan to Newell on January 9 and was scheduled to complete that run Tuesday with the installation of the final manhole just south of the intersection with Fletcher Avenue. Once that is completed crews will move down to the Logan-Lucas intersection to begin connecting the new sanitary main to the existing sanitary main. The work will necessitate the complete closure of the intersection.

Residents on Lucas north of the Logan intersection will have access from the Newell end of Lucas Street. Residents on Lucas south of the Logan intersection will have access from West 8th Street. Residents on Logan will have access from Climer Street.

DETOUR – Northbound traffic on Lucas will be detoured on to West 8th Street, to Broadway, to Newell, and back to Lucas Street. Southbound traffic on Lucas will be detoured on to Newell, to Broadway, to West 8th Street, and back to Lucas Street.

NEXT STEP – Once the work in the Lucas-Logan intersection is completed, Haggerty Earthworks LLC will be moving to the Logan-Climer intersection. The final major segment of Phase 5 is Climer Street from Logan to Lucas with both water main and sanitary storm sewer separation work to be completed.

Pavement restoration will begin as the weather permits including the completed sections on Lucas from Green to West 4th streets, and on Lucas from Logan to Newell. Once the construction season begins in earnest, pavement restoration will follow the completion of underground work.

LET US KNOW – Contact the City of Muscatine for more information on projects, services, and with questions or concerns regarding a project or service. Feedback may be provided by sending an email to feedback@muscatineiowa.gov

You can also click on the green Muscatine Connect button in the upper left of the City of Muscatine website home page to view categories that you can open to send a comment, ask a question, or report a problem to City staff. Or you can click on Request Form to go directly to the request page.

To download the Muscatine Connect app to your smartphone visit the iPhone App Store or Google Play. Once installed you will be able to send information and pictures directly from your smart device to a specific department. It is our policy to respond within 24 hours during the work week and to resolve any issues within five business days, if possible.

Categories
City of Muscatine Press Releases

Lane restriction begins Monday on section of Lucas

MUSCATINE, Iowa – Lucas Street will be reduced to one lane of traffic from Newell to Logan starting Monday, Jan. 9, 2023, as Phase 5 work on the West Hill Sanitary and Storm Sewer Separation Project (WHSSSP) resumes.

Underground sewer replacement work resumes next week with the westbound lane closed at Logan and at Newell. Westbound traffic will be detoured onto Logan, to Newell, and back to Lucas. Eastbound traffic will not be affected by the lane closure.

While work resumes on Phase 5, Department of Public Works staff and Stanley Consultants are wrapping up preparation for Phase 6. A public meeting will be held on Tuesday, Jan. 10, to introduce Phase 6A of the WHSSSP. The meeting will be an open house format and held from 5-7 p.m. on Tuesday, Jan. 10, in the City Council Chambers at Muscatine City Hall.

The meeting is specifically for residents directly affected by the project and to answer any questions they may have regarding their easement agreements. The general public is also welcomed to attend.

Residents on Sycamore Street from East 8th Street to West Fulliam and those on West Fulliam from Sycamore Street to just west of Nelson Drive will be mostly affected by Phase 6A along with some residents on 9th, 10th, and 11th streets between Sycamore Street and Iowa Avenue.

If you have a question, comment, or request, visit Muscatine Connect, or download the app from the AppStore or GooglePlay. 

Categories
City of Muscatine Press Releases

Block of Lucas to remain closed through January 13

MUSCATINE, Iowa – Lucas Street will remain closed to through traffic from North Houser Street to Westwood through January 13, 2023, weather permitting. Needham Excavating has completed installation of sewer and water connections for the Muscatine Community School District Centralized Kitchen that is currently under construction, and is now preparing the section for repaving.

The current forecast indicates that the next available day to pour concrete will be January 9, which means that the section could be reopened to traffic at the end of the day on January 13. That schedule is depending on the weather, however.

Westbound traffic on Lucas is currently detoured north on Houser and then west on Cedar. Eastbound traffic on Lucas is detoured south on the U.S. 61 Bypass to Hershey then east to Houser.

If you have a question, comment, or request, visit Muscatine Connect, or download the app from the AppStore or GooglePlay. 

Categories
City of Muscatine Press Releases

Block of Lucas Street closed to traffic January 3-10, 2023

MUSCATINE, Iowa – Lucas Street will be closed to traffic from North Houser Street to Westwood starting January 3, 2023. The closure is expected to last approximately one week. Needham Excavating has requested the street closure to install sewer and water connections for the Muscatine Community School District Centralized Kitchen that is currently under construction.

Westbound traffic on Lucas will be detoured north on Houser and then west on Cedar. Eastbound traffic on Lucas will be detoured south on the U.S. 61 Bypass to Hershey then east to Houser.

If you have a question, comment, or request, visit Muscatine Connect, or download the app from the AppStore or Google Play. 

Categories
City of Muscatine Press Releases

Block of Logan to be closed to through traffic starting August 15

MUSCATINE, Iowa – Logan Street will be closed to through traffic between Lucas and Climer streets starting Monday (Aug. 15) according to the Department of Public Works. 

West Hill Sanitary & Storm Sewer Separation Project (WHSSSSP) work has moved west out of the ravine through the alley that ends at Logan Street. The contractor is now ready to begin work on Logan Street with the stretch from the alley toward Lucas accomplished first. The section between the alley and Climer will follow.

During the winter new sanitary sewer pipe was placed in the ravine from High Street toward the intersection of the east/west and the north/south portions of the alleys connecting Climer and Logan. Ravine work resumed Tuesday and has been completed up to Logan Street. Access to driveways in the alleys are being temporarily restored with a rock surface until paving portions of the alley can be completed.

Local traffic will be permitted on Logan as the underground work is being completed. Once the underground work has been accomplished, the block of Logan will be prepped for paving and repaved.

Repaving Climer Street from the 700 block to High Street started Wednesday with curb and gutter on both sides of the street. The driving lanes were being poured on Friday but work was halted due to the brief rain shower over the noon hour. Climer will be opened to traffic, at least temporarily, next week but the exact day is dependent on the weather. Once opened, however, there will be some lane restrictions as work on sidewalks and driveways is completed.

Underground work on Climer from High to Logan will resume once work on Logan between Lucas and Climer has been completed. Advance notification will be given when this section of Climer is closed to traffic.

Lucas Street remains closed to traffic from Busch to West 8th as the contractor prepares this section of Lucas for repaving, which should be accomplished over the next two weeks depending on the weather.

Project work moving east on Lucas Street from the West 8th Street intersection started Wednesday as sanitary sewer pipe is replaced from West 8th up to the curve where Lucas becomes West 4th Street. Progressive closures of Lucas Street will occur moving to the east including the Main Street intersection. 

There will be limited access available with this section of Lucas reduced to one lane where the underground work is being completed. A temporary driving surface will be provided behind the underground work once the contractor determines it is safe to do so. Driveways along the work area will be inaccessible while the sewer is being installed, but the contractor will attempt to restore driveway access as quickly as possible with a temporary driving surface.

Categories
City of Muscatine Press Releases

Lucas closed West 8th to West 4th starting Wednesday

MUSCATINE, Iowa – Lucas Street will be closed to traffic from West 8th to just past Main Street starting Wednesday morning, and travelers can expect Logan Street to be closed from Lucas to Climer within the next week or two according to the Muscatine Department of Public Works as part of the West Hill Area Sanitary and Storm Sewer Separation Project.

Repaving Climer Street from the 700 block to High Street is scheduled to begin Wednesday with curb and gutter on both sides of the street. The driving lanes are tentatively scheduled to be poured on Friday. Once cured, access to the Climer will be permitted with some lane restrictions as work on sidewalks and driveways is completed.

Project work will be moving east on Lucas Street from the West 8th Street intersection starting Wednesday morning (August 10) as the sanitary sewer pipe is replaced from West 8th up to the curve where Lucas becomes West 4th Street. Progressive closures of Lucas Street will occur moving to the east including the Main Street intersection. 

There will be limited access available with Lucas reduced to one lane where the underground work is being completed. A temporary driving surface will be provided behind the underground work once the contractor determines it is safe to do so. Driveways along the work area will be inaccessible while the sewer is being installed, but the contractor will attempt to restore driveway access as quickly as possible with a temporary driving surface.

Project work near Logan Street will move west out of the ravine through the alley that goes toward Logan Street this week. During the winter new sanitary sewer pipe was placed from High Street toward the intersection of the east/west and the north/south portions of those alleys.

Ravine work began Tuesday and is expected to be into the alley intersection by Wednesday morning at which point all access to the alley up to Logan will be closed. As soon as the sewer is run up to Logan Street, access to driveways in the alleys will be restored. Eventually that portion of the alley will be paved but a rock surface will be placed as quickly as possible when the work in the alley is complete for access to the driveways.

Categories
City of Muscatine Press Releases

Construction Update: Busch-Lucas intersection to close July 11

MUSCATINE, Iowa – The intersection of Busch and Lucas streets will be closed to traffic starting Monday (July 11) as part of Phase 5 of the West Hill Sanitary and Storm Sewer Separation Project according to officials at the Department of Public Works. It is anticipated that the closure will last six weeks.

In order to maintain access to the residents of Busch Street, the City of Muscatine obtained permission from the owner of property located at the end of Greenwood Drive to use that private property to construct a connector path from the alley behind Busch Street to the end of Greenwood Drive. The path has been completed but is open to local traffic only. 

Busch Street Bypass 7-11-2022 (JPG)Using the route from Lucas down Greenwood Drive to the connector to the alley and to Busch provides access to all the homes on Busch during the Lucas intersection closure. Once the Busch-Lucas intersection is reopened, the temporary access road will be removed and reseeded to return it to its original condition.

Since the temporary access area runs next to a ravine, there have been problems in the past with people using that area to dump trash and other materials. If ay such activity is witnessed during this period of use to access Busch Street please notify the Police Department.

Work on repaving the West 8th and Lucas intersection will also resume next week following the completion of underground work by Muscatine Power & Water. Repaving is also expected for the Climer Alley. The paving is expected to take two weeks, weather permitting. Once completed, West 8th Street will be completely open.

Lucas Street will continue to be closed at the West 8th intersection as underground work continues toward Busch Street and will begin soon heading toward Green Street.

Underground work on Climer Street is making progress toward High Street as Haggerty Earthworks works in short sections to minimize disruption of accessibility to resident homes in the work area. Once the contractor completes work through the High Street intersection, underground operations will move to Logan while Climer is repaved from High to West 8th.

GRANDVIEW AVENUE

The Grandview Avenue intersection with Houser and Sampson remains closed to traffic with most underground work crossing Grandview completed. This is the final major intersection of the Grandview Avenue Reconstruction Project with Heuer Construction, Inc., anticipating that two-way traffic on Grandview will be restored by August 1, weather permitting.

The full closure of the intersection will be implemented on Sampson east of the Canadian Pacific Railroad crossing, Houser north of the Mittman intersection, Mittman just south of the intersection with Houser, Grandview 200 feet south of the intersection with Houser-Sampson, and Grandview from the Cheri Top south.

Access to all Grandview Avenue businesses south of the Musser intersection to the Houser-Sampson intersection will be from the intersection with Musser.

Through traffic coming from the south will be detoured west onto the Highway 61 by-pass to the Hershey exit and then to Mississippi Drive, or east on Dick Drake Way to Stewart Road/Oregon and back to Grandview.

The final section of Grandview will be rocked and prepped for paving starting Monday (July 11). Tentative plans are to have Grandview Avenue completely open for two-way traffic once the new pavement cures, but the Sampson and Houser legs of the intersection will remain closed as they will be reconstructed after Grandview is opened.

The Grandview Avenue Reconstruction Project remains on schedule. Once the roadway is completed, Heuer will complete sidewalks, driveways, and landscaping in each of the two phases. The project is tentatively scheduled to wrap up November 2022.

FULL DEPTH PATCHING BEGINS ON ISETT

Removal and replacement of sections of the Isett Avenue pavement continue as the final segment of the 2021-2022 Full Depth Patching program. Heuer Construction, Inc., are repairing areas of the Isett Avenue pavement from the Heinz pedestrian crossing to Clay Street.

Drivers are urged to slow down, obey traffic control devices, watch out for construction workers, and plan for extra time when driving through the construction zone.  Please find alternate routes of travel if possible.

The City of Muscatine and the Iowa DOT reminds motorists to drive with caution, obey the posted speed limit and other signs in the work area, and be aware that traffic fines for moving violations are at least double in work zones. As in all work zones, drivers should stay alert, allow ample space between vehicles, wear seat belts, and be aware of construction workers. Use an alternate route if possible.

Click on CONSTRUCTION to visit the Department of Public Works Construction Projects page where more information can be found on City of Muscatine construction projects. An interactive map is available showing current street closures and street work.

If you have a comment or concern, please email feedback@muscatineiowa.gov or pwrequest@muscatineiowa.gov. A staff member will respond within 24 hours.

Categories
City of Muscatine Press Releases

Lucas-West 8th intersection to be closed six weeks

MUSCATINE, Iowa – The intersection of West 8th and Lucas streets will be closed to all traffic beginning Monday (April 4) as part of Phase 5 of the West Hill Sanitary and Storm Sewer Separation Project. The full closure will last approximately six weeks depending on the weather.

 

Road Closure Diagram 4-4-2022 V2 (JPG)Limited access will be permitted on Lucas Street from Main Street on the east side of the intersection and from Busch Street on the west side. Limited access will also be permitted on West 8th Street from Broadway to the Lucas Street intersection and from Main Street to the Lucas Street intersection. The Whicher intersection will remain open.

 

In addition to the work at the Lucas and West 8th intersection, general contractor Haggerty Earthworks, LLC, plans to close Climer Street from West 8th to High starting on Wednesday (April 6). Local traffic only will be permitted as sanitary and storm sewer separation work begins on this segment of Phase 5.

 

The contractor anticipates keeping all driveways accessible for residents for as much as possible from Busch to Main on Lucas and from West 8th to High on Climer. Periodic closures will occur as underground work progresses. Full closures will occur during the removal and replacement of the pavement from curb to curb. Residents will be notified in advance of the full closures.

 

Sewer project work on Lucas Street in 2022 will focus on the area from Busch Street to the curve in Lucas Street just past Green Street and include the 900, 1300, 1400, and 1500 bl;ocks of Lucas.

 

Sewer project work on Climer Street in 2022 will begin in the 700 block of Climer and move toward the Lucas Street intersection. 

 

FULL DEPTH PATCHING CONTINUES

 

The two emergency repairs, on Hershey and Liberty, that are part of the 2022 Full Depth Patching Program are nearly complete but lane restrictions may continue into next week as concrete replacement continues. Liberty has been used as a detour during the Grandview Avenue reconstruction and the higher-than-normal traffic created buckles in the roadway.

 

Once the emergency repairs are completed, Heuer Construction, Inc., will move to 1608 Cedar Street (near the intersection with Parham).

 

Also included as part of the 2022 contract is Isett Avenue (Bidwell Road to the Heinz pedestrian entrance), Houser Street (Fulliam Avenue to Dawson Street), Stewart Road (Oregon Avenue to Wallace Street), Robin Road (Sunrise Circle east to end of the concrete), Frontage Road (Cleveland Street to Ford Avenue), and Devitt Avenue (Ridgewood Avenue to Pinefield Street). Additional emergency repairs may be added if time and money remain in the contract.

 

Additional traffic notes:

 

  • Heuer Construction, Inc., has closed one outside lane of Park Avenue from Washington to the Mad Creek Bridge on East 2nd Street to work on the Iowa DOT punch list for the Park Avenue 4-to-3 Lane Conversion Project that was substantially completed last fall.
  • Musser Street is closed from the intersection with Wisconsin and Baker to the Grandview intersection as the east side of the Musser-Grandview intersection is reconstructed as part of the Grandview Avenue Reconstruction Project.
  • Traffic restrictions continue on Grandview Avenue from Houser to Musser streets as underground work and pavement removal continue. The contractor maintains customer and delivery access to all businesses as Phase II of the Grandview Avenue Reconstruction Project continues. 

 

Drivers are reminded to slow down and use caution when travelling through the construction zone, obey traffic control devices, and be aware of workers. Use an alternate route if possible.

 

For more information on City of Muscatine construction projects click on CONSTRUCTION to visit the Department of Public Works Construction Projects page.

 

If you have a comment or concern, please email feedback@muscatineiowa.gov or pwrequest@muscatineiowa.gov. A staff member will respond within 24 hours.